News Staff
Wednesday, April 16, 2025
constructing highway US-83 which requires removing and replacing the existing concrete pavement. The project also includes improvements to sidewalks, storm sewer, roadway lighting, and repairs to the bridge over Minnechaduza Creek. The City of Valentine plans to update city-owned sanitary sewer and water main along US-83/4th Street concurrently with this project. The project will be constructed in phases. The phase from the US 83 and N-12 junction to Edna Street will require complete closure and traffic will be detoured on Cherry, West 3rd, and Edna Streets. The phase from Edna Street to the end of the project will be constructed under traffic with lane closures controlled by temporary traffic signals. Access to adjacent properties will be maintained during construction but may be limited at times due to phasing requirements. Motorists are reminded to drive cautiously in and near work zones, to buckle up, and to put phones down.